AUSTRALIAN NATIONAL UNIVERSITY Monthly
Report 10 Created: 4 December 2000 Last modified: 5 December 2000 |
MONTHLY REPORT FOR NOVEMBER 2000
Jan van Harmelen
Research
School of Astronomy and Astrophysics
Institute
of Advanced Studies
Australian
National University
Revision
History
|
Revision No. |
Author & Date |
Approval & Date |
Description |
|
Revision 1 |
Jan
van Harmelen 4 December 2000 |
Peter McGregor 5 December 2000 |
Original document. |
|
|
|
|
|
Contents
Some progress was made identifying suitable
guide stars for potential NIFS targets. Assistance will be available during
December to continue this investigation.
This monthly report on
NIFS activities covers the five week period from 30 October to 1 December2000.
Just before the end of
the reporting period, it was announced that the NIFS contract had finally been
formally executed. RSAA will now continue procurement for the NIRI duplication
work.
The continuing
non-availability of NIRI as-built documentation hampers progress on CC and IS
software development, control system design and procurement, and cryostat and
OIWFS duplication.
There have been no
further developments in the search for competent mechanical design staff.
An electronics
technical officer vacancy still exists. We are also exploring the possibilities
for filling the temporary position to allow the fabrication of the NIFS control
system.
The flip mirror
assembly design has been completed. Design of the system from pick-up mirror to
slicer has been completed. These designs have to be integrated with the overall
system design.
The mechanical
workshop has continued to fabricate components for the NIRI duplication. The
design modifications for the fixed OIWFS detector mount have been revised. The
OIWFS optable machining is ready to be ordered. The OIWFS lenses have been
ordered from Janos.
More quotes have been
received for the control system hardware. Some still remain outstanding.
Purchasing is ready to be commenced.
There has been no
worthwhile progress with the CC and DC software, due to other scheduled
commitments.
The design of the
detector mounting board has been revised. Experiments at IfA indicate that the
detector bus output cannot drive the amplifiers we intended to use with the
settling time that is required. Klaus Hodapp suggests the use of J270 JFETs,
which will require tighter control of amplifier temperature. A liquid nitrogen
dewar was fitted with some parts to assess temperature control performance of
the Lakeshore controller under various circumstances. The dewar had a leak and
did not hold vacuum long enough to do any sensible experiments. The fittings
were transplanted to another dewar, but further experiments have not yet taken
place.
The schedule will
undergo thorough revision in preparation for CDR.
|
Task WBS |
hrs |
Finish Date |
Title |
Deliverables |
|
2.5.2.1 |
109(1) |
01 Dec 00 |
Determine Optical Fold Layout |
Drawing and Zemax files |
Notes:
1. This task was marked as completed in July, but the revision of the optical design last month required that the optical fold layout be reconsidered.
2.1.1
NIFS Critical
Design - Project Management
A continuing task. JvH: 29 hrs.
2.1.6
PS Miscellaneous
A continuing task to record various activities.
No progress this period.
2.2.1
Revise OCDD
No progress this period.
2.2.2
Revise FPRD
No progress this period.
2.2.3
Science Case
Looking for more targets: PM: 83 hrs.
2.3.1
Requirements
Analysis
No progress this period.
2.4.6
Revise Error
Budget and Specify Tolerances
No progress this period.
2.4.16
Specify and
Negotiate IFU Machining
JH: 72 hrs.
2.4.17
Negotiate Diamond
Turning of Non-IFU Mirrors
JH: 29 hrs.
2.5.2.3
Disperser
Turret/Bypass Mirror Design
Continued: LP 192 hrs.
2.5.2.4
Develop IFU
No progress this period.
2.5.2.6
Design Array and
TriFold Mirror
No progress this period.
2.5.2.7
Detector Mount
Design
PC: 10 hrs.
2.5.2.10
Design Entrance
Turret
Assembly design for entrance turret. PC: 78 hrs
2.5.2.12
Camera Mount
Design
No progress this period.
2.5.2.13
Design Baffle
System
No progress this period.
2.6.2.1
Detector Mount
Board Wiring Design
MDD: 21 (Effort in previous months, although
included in the total number of hours reported for the financial statement, was
omitted from this listing. It amounts to 67 hrs)
2.6.2.2
Detector Mount
Board Wiring Layout
WG: 30 hrs.
2.7.4
Component
Controller Software
MJ: 10 hrs.
2.7.6 Detector Controller Software
PJY: 27 hrs.
4.1.1
Cryostat and
OIWFS Duplication – Project Management
A continuing task. JvH: 14 hrs.
4.2.1
Cryostat and OIWFS
Duplication – Design and Supervision
A continuing task. GJ and others: 206 hrs.
4.2.2 Cryostat and OIWFS
Duplication – Parts Fabrication
Workshop
effort 444 hrs this period.
4.3.1
Control System –
Design and Supervision
Prepare purchasing list and request quotes.
MID: 16.5 hrs.
5.8.8.1
Test Cryostat
Temperature Control – Design Control system
MDD: 14 hrs.
5.8.8.2
Test Cryostat
Temperature Control – Wiring
WG: 95 hrs.
No documents were issued during the reporting period:
|
Document ID |
Rev |
Date |
Title |
|
|
|
|
|
The current schedule
is the schedule included in the “NIFS Revised Costing”. A schedule revised for
the expected delivery dates of the detectors and the late start on cryostat and
OIWFS duplication was developed. It also takes into account the proposed
delayed CDR. This revised schedule was submitted during September 2000. The
schedule will be revised again and the new schedule will be presented in the
CDR documentation.
20 people have
contributed to the NIFS project during this period. They worked a total of 1342
hours, bringing the total for the project to 6383 hrs, which represents
approximately 21.0 % of the total number of hours in the current project plan.
Listed below are the milestones defined in the NIFS contract. No
milestones were due during the reporting period.
|
Event |
Date |
Status |
|
(1)Contract fully signed |
August 2000 |
Completed |
|
(2) Placement of order for vacuum
jacket forging |
August 2000 |
Completed |
|
(3) AURA approval of Final FPRD
and OCDD |
5 December 2000 |
To be submitted with CDR
documentation |
|
(4) AURA approval of Detailed
Design Documentation after CDR |
January 2001 |
|
|
(5) Start of first Cryostat and
OIWFS cooldown |
14 May 2001 |
|
|
(6) Completion of Cryostat and
OIWFS Duplication (As task is described in Conceptual Design Documentation) |
4 October 2001 |
|
|
(7) Completion of Spectrograph
Construction (As task is described in Conceptual Design Documentation) |
22 March 2002 |
|
|
(8) Authorization to ship
instrument given by AURA |
19 July 2002 |
|
|
(9) Completion of all Work and
Final Acceptance given by AURA |
1 October 2002 |
|
The exchange rate used
is the rate applicable to a particular transaction, or the rate on the last day
of the reporting period. On 1 December 2000 the rate was 0.528.
No income was gained
during the reporting period.
The NIFS account was
charged for 1260 hrs of work from 30 October to 1 December 2000. This is the
total number of hours (1342) minus the hours for the Project Scientist (82).
The total charge is US$44,100 (A$83,523)
The following
expenditure was incurred during the reporting period.
2.6.2.1 Detector Mount Board Design
Electronics Components US$ 96 A$ 181
5.8.9
Control System -
Lakeshore temerature controller and sensors
US$ 7,621 A$14,434
4.6.1
NIRI Duplication
– Consumables
Freight & customs US$ 200 A$ 378
5.3.7
Spectrograph
Optical Fabrication – Field Slicer
Sheet metal material US$ 109 A$ 207
-------------- ------------
total US$ 8,026 A$15,200
The ANU accounting
system also includes ‘commitments’, where a purchase order has been raised, but
goods or services have not yet been delivered, invoiced and paid. New
commitments are listed here, but not included in the financial status report.
2.6.2.1 Detector Mount Board Design
Detector Sockets US$ 571 A$ 1,082
4.2.2.5
NIRI
Duplication – Cryocooler assembly
Material –Copper US$
1,431 A$ 2,710
4.2.2.24
NIRI
Duplication – OIWFS Lenses
Janos US$29,153 A$55,214
4.2.2.26 NIRI Duplication – Miscellaneous Purchased
Items
Titanium US$ 972 A$ 1,840
-------------- ------------
total US$32,038 A$60,677
|
Date |
Description |
Income (US$) |
Income (A$) |
Outgoings (US$) |
Outgoings (A$) |
|
29 Jul 00 |
Labour |
|
|
37,940 |
64,524 |
|
01 Sep 00 |
Labour |
|
|
48,125 |
83,696 |
|
01 Sep 00 |
Other Costs |
|
|
1,607 |
2,773 |
|
29 Sep 00 |
Labour |
|
|
44,205 |
82,626 |
|
29 Sep 00 |
Other Costs |
|
|
7,748 |
14,483 |
|
27 Oct 00 |
Labour |
|
|
35,525 |
68,056 |
|
27 Oct 00 |
Other Costs |
|
|
12,014 |
23,015 |
|
01 Dec 00 |
Labour |
|
|
44,100 |
83,523 |
|
01 Dec 00 |
Other Costs |
|
|
8,026 |
15,200 |
|
27 Oct 00 |
Balance |
|
|
239,291 |
437,896 |
The only technical
problem impeding project progress is the unavailability of as-built information
on NIRI and its control software and examples of manuals and plans.
The purchase and
delivery of items on the critical path of the project may be delayed because of
the delayed execution of the NIFS contract and other delays caused by it.
With the signing of
the NIFS contract, the financial problems have been solved.
The following Action Items are outstanding.
|
No. |
Action |
Who |
Status |
Due Date |
|
1 |
ICD16
Parameter Definition Format. Clarification |
RAN |
Closed. PJY to contact Steve
Wampfler |
|
|
2 |
Revise
NIFS schedule to reflect FPA delivery lead time |
JvH |
Closed Plan updated |
|
|
3 |
Generate
ordered list of "As Built" NIRI drawings |
JvH |
Closed List provided |
|
|
4 |
Negotiate
delivery schedule for As Built NIRI drawings with IfA |
RAN |
|
|
|
5 |
Determine
status of NIRI manuals |
RAN |
|
|
|
6 |
Determine
specifications and manufacturer of NIRI CaF2 window |
RAN |
Closed Information provided |
|
|
7 |
Make
tar archive of operational NIRI software |
RAN |
Closed |
|
|
8 |
Determine
status of IfA OIWFS fabrication |
RAN |
|
|
|
9 |
Send 7
cryo stepper motors to ANU |
RAN |
1 received |
|
|
10 |
A
flip-in acquisition mirror will be incorporated into the design |
JvH |
Closed. Documentation to be changed
as required |
|
|
11 |
Send examples of Commisioning and Verification Plans |
RAN |
|
|
|
12 |
Relay urgency of NIFS contract approval |
RAN |
Closed NIFS contract signed |
|
|
13 |
Check impact of late OIWSF parts delivery by UH on NIFS schedule |
JvH |
Closed. Early May 2001 is latest
delivery possible on the currently proposed plan. |
|