![]() |
Research School of Astronomy and Astrophysics
Mount Stromlo and Siding Spring Observatories
|
|
Current NewsCCD ContaminationStatus, February 22nd, 2005The Imager CCD camera is now back at Siding Spring and was used forobserving on the 16th, 17th and 18th February. The data has yet to be inspected but a cursory glance indicates there may well be some residual cleaning marks, most easily seen in U and B frames. These appear as low level, vertical, 'streaky' marks and should be removed during flat-field exposure processing. All other Detector characteritics are nominal.
The new GAIN option has now been added to the Cicada release as
Status, February 7th, 2005The Imager Science detector is now operational in the science cameraEarly tests indicate that the device has survived in-tact after the clean at E2V in January. 2 spot QE tests performed last Friday at 400 and 500 nm show a responsivity of about 90%, indicating that the AR coating has not been damaged. Similarly a noise test performed on the detector using the Bias frames from the QE test showed a read-out noise of about 4.5e rms. Further tests will be performed this week then the Imager will go back to Siding Spring for observer's use.
The image 'glitching' problem has now also been resolved. The source of Pre and Post-clean images from the E2V CCDThe 1st of the following 2 images was taken just after the contamination occuredand clearly shows the 'spattered' material on the CCD surface. The Images are zero exposure frames, with the intrenal dewar LEDs illuminated for 80ms, after the CCD is cleared and just before the CCD is read-out.
Status, January 31st 2005The E2V CCD has now arrived back at RSAA and is ready to be mounted in the Imager.This will happen later this week after the work to seek out the cause of the current image glitching, i.e. image moving within the frame between exposures, has been found. Current suspect is related to whether the user requests a frame to be 'pre-flushed' i.e. cleared of charge, before the exposure takes place. The problem doesn't occur if the CCD is NOT 'pre-flushed'... Strange...!!!
Status, January 24th 2005The Imager CCD was DC tested on Friday and passed the room Temp. (RT) test. Paul Jorden issending the device back to us today (Monday 24th) and I hope it will arrive late this week - or early next week. The successful RT DC test almost certainly indicates that the CCD will image properly. This will be checked out when it arrives here before transport to SS With this prompt return of the detector - there seems little point in delivering the Imager to SS with the Engineering CCD - so the head will remain here - pending a re-fit of the science detector.... -:))
Status, January 21st 2005The E2V Imager CCD has been DC tested at room temp - and was working ok when itarrived at E2V. It was cleaned yesterday (Thurs 20th) and then baked out to remove any water vapour contamination etc. It is due to be room temperature, DC tested again today - so we should know by Monday whether the CCD has survived the process. If it is still operational it will be immediately returned to us - so we should have it back by late next week, or early the following week Imaging tests will then be performed and the the Dewar returned to SSO as soon as possible after completion of these tests.
Status, January 19th 2005The CCD has now reached E2V - but not Paul Jorden. He has stated that once he receives thedevice, it will be DC tested (at room temperature), inspected and if possible, with our approval, cleaned. After this the device will be DC tested (again at RT) - this should confirm the device's operational state. It will then be returned to us. This should take between 3-4 weeks
The CCD will then have to be installed in the Imager dewar and some imaging tests performed
Pictures of Rebuild of E2V Imager Dewar
Status, January 11th 2005
A report from Mike Dopita has alerted me to tha fact that the 2.3m Imager dewar has The 2.3m E2V CCD Imager dewar was therefore returned to RSAA on the 4th January - for inspection.
The dewar was found to be contaminated with material from the getter unit (used to maintain
The E2V 4240 CCD was removed from the Imager Dewar on the 6th January and placed in a carton
In the meantime, the Engineering grade CCD is being characterised, using the new test dewar
There will be a first cool-down today (11th January) and characterised after which, if found Pictures of Getter - Rear of E2V Imager Dewar
Enquiries about the E2V Contamination Issue? detman@mso.anu.edu.au |
||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||||
|
Page last updated: 11 August 2006 Please direct all enquiries to: Webmaster Page authorised by: Director, RSAA |
| The Australian National University — CRICOS Provider Number 00120C |